They are building a medium-density residential subdivision of 96 dwelling units on 12.1 acres on East 8th St.
Progress-Schedule:
April 28 - May 8, 2025 - They located utilities in street. Paved back up.
Street signs on May 9 say Construction May 10 - July 10
May 10 - May 23 - Leveling and excess dirt removal
July-Aug Utility lines, Water, Sewer, Electrical, Cable/internet, ... installed
Aug. 29 - sidewalks poured.
Contacts:
Del Fairchild, Century Communitdies:
Del.Fairchild@centurycommunities.com
916 257-7206
Davis Planning Division:
planning@cityofdavis.org 530 757-5610
Construction progress:
May 4 - Location of utilities.
The street was dug up with a few small holes to locate utilities, but then paved over.